Back to projects

Detailed Stormwater Management Assessment and Analysis for Disaster Mitigation and to Accommodate Future Community Growth

Mississaugas of Scugog Island First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$44,676
Federal share43%

of $104.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Dec 1, 2017(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2017
  • Construction end3 months lateforecast Sep 30, 2019

Also in Mississaugas of Scugog Island First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51512 in the federal list. How to read these figures.