Rehabilitation and Optimization of the Moose Deer Point First Nation Water Treatment System
Moose Deer Point First Nation, Ontario
Federal contribution
$42,241
Federal share50%
of $84.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Moose Deer Point First Nation
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Jun 1, 2018(actual)
Against the original forecast
- Construction start9 months earlyforecast Jan 1, 2017
- Construction end5 months lateforecast Dec 31, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51514 in the federal list. How to read these figures.