Water Supply Feasibility Study and Design for Community Lot Servicing

Aamjiwnaang First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$10,625
Federal share16%

of $65.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Aamjiwnaang First Nation
Construction start
Oct 5, 2017(actual)
Construction end
Sep 20, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017
  • Construction end8 months lateforecast Jan 31, 2018

Also in Aamjiwnaang First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51515 in the federal list. How to read these figures.