Replacement of Existing Generator at Lakeview Booster Station
M'Chigeeng First Nation, Ontario
Federal contribution
$80,000
Federal share50%
of $160.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020202120222023
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- M'Chigeeng First Nation
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Feb 23, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 24, 2017
- Construction end8 weeks lateforecast Dec 31, 2022