Truck Route Renewal for RTAC Loading
Federal contribution
$300,903
Federal share33%
of $902.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Emerson-Franklin
- Construction start
- Oct 15, 2017(actual)
- Construction end
- Sep 14, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 1, 2017
- Construction end7 weeks earlyforecast Oct 31, 2018