Arnaud and Area Potable Water Supply
Federal contribution
$1.3M
$1,254,372
Federal share36%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of Emerson-Franklin
- Construction start
- Oct 26, 2016(actual)
- Construction end
- Feb 6, 2018(actual)
Against the original forecast
- Construction start6 months earlyforecast May 1, 2017
- Construction end8 weeks earlyforecast Mar 31, 2018
Also in Emerson-Franklin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47125 in the federal list. How to read these figures.