Community Hall Renovation and Addition
Federal contribution
$250,000
Federal share33%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
20182019
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Gilbert Plains
- Construction start
- May 28, 2018(actual)
- Construction end
- Jan 15, 2019(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Feb 15, 2019
Also in Gilbert Plains
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51583 in the federal list. How to read these figures.