Municipality of Gilbert Plains Retention Dams
Federal contribution
$145,500
Federal share60%
of $242.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2021
2022202320242025
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Gilbert Plains
- Construction start
- Aug 14, 2023(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction end4 weeks lateforecast Nov 30, 2024
Also in Gilbert Plains
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58360 in the federal list. How to read these figures.