Water and Sewer Upgrading Water Street
Carbonear, Newfoundland and Labrador
Federal contribution
$149,561
Federal share30%
of $498.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Carbonear
- Construction start
- Apr 29, 2019(actual)
- Construction end
- Jul 31, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2018
- Construction end15 months earlyforecast Oct 30, 2020
Also in Carbonear
- Upgrades to Route 70- Interchange at Valley Road and Route 75 - Veterans Memorial Highway$2.2M
- Water System Upgrading$807.0K
- Adelaide Street Water Sewer Storm Street Upgrades Ph2$587.6K
- Water Street Water, Sewer and Street Upgrading$517.8K
- Water Street - Water, Sewer and Street Upgrading Phase 3$473.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51592 in the federal list. How to read these figures.