Back to projects

Water and Sewer Upgrading Water Street

Carbonear, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$149,561
Federal share30%

of $498.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Carbonear
Construction start
Apr 29, 2019(actual)
Construction end
Jul 31, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2018
  • Construction end15 months earlyforecast Oct 30, 2020