Dugald Water System Upgrade
Federal contribution
$716,833
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
20182019202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Springfield
- Construction start
- Jan 15, 2019(actual)
- Construction end
- Jun 15, 2022(actual)
Against the original forecast
- Construction start5 months earlyforecast Jun 1, 2019
- Construction end2 weeks earlyforecast Jun 30, 2022