Donaldson Drain Diversion

Springfield, Manitoba

completeDisaster MitigationRNIS
Federal contribution
$223,875
Federal share50%

of $447.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2021
2021202220232024
Built

Approved 6 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 29, 2024(actual)
Construction end
Oct 31, 2024(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 15, 2024