Upgrade Sewage Pumping Stations
Greenspond, Newfoundland and Labrador
Federal contribution
$69,521
Federal share29%
of $240.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Greenspond
- Construction start
- Apr 1, 2018(actual)
- Construction end
- Oct 1, 2018(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 15, 2018
- Construction end7 weeks lateforecast Aug 15, 2018