Chlorination System Replacement

Greenspond, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$70,328
Federal share40%

of $175.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
2021
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Greenspond
Construction start
Feb 17, 2021(actual)
Construction end
Aug 18, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Dec 1, 2020
  • Construction end7 months lateforecast Jan 15, 2021

Also in Greenspond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56958 in the federal list. How to read these figures.