Barrhead Wastewater Treatment Plant Upgrades
Federal contribution
$645,688
Federal share50%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2018
2018201920202021
Built
Approved 7 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Barrhead
- Construction start
- Mar 1, 2019(actual)
- Construction end
- Sep 27, 2021(actual)
Against the original forecast
- Construction start2 months earlyforecast May 1, 2019
- Construction end3 months earlyforecast Dec 31, 2021
Also in Barrhead
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51718 in the federal list. How to read these figures.