Schedule
Announced and approvedNov 13, 2017
201820192020202120222023
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- Jul 1, 2020(actual)
- Construction end
- Feb 17, 2023(actual)