Back to projects

Radio communication system - phase 2

Longueuil, Quebec

completePublic TransitPTIF
Federal contribution
$938,186
Federal share50%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 13, 2017
201820192020202120222023
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 1, 2020(actual)
Construction end
Feb 17, 2023(actual)

Also in Longueuil

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51735 in the federal list. How to read these figures.