Thirty-one (31) Wheelchair Accessible Shelters
St. John's, Newfoundland and Labrador
Federal contribution
$219,917
Federal share49%
of $453.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2018
20182019
Built
Approved 11 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of St. John's
- Construction start
- Jun 13, 2018(actual)
- Construction end
- Apr 30, 2019(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 31, 2017
- Construction end6 months earlyforecast Oct 31, 2019
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51790 in the federal list. How to read these figures.