Back to projects

Universal accessibility plan

Montréal, Quebec

completePublic TransitPTIF
Federal contribution
$74,664
Federal share50%

of $149.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2018
20172018
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 1, 2016(actual)
Construction end
Apr 30, 2017(actual)

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51797 in the federal list. How to read these figures.