Back to projects

Study on transit demand

Montréal, Quebec

completePublic TransitPTIF
Federal contribution
$373,847
Federal share50%

of $747.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2018
201820192020
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 1, 2018(actual)
Construction end
Dec 31, 2019(actual)

Also in Montréal