Transportation West Fleet Upgrade
Alberton, Prince Edward Island
Federal contribution
$33,225
Federal share33%
of $99.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 25, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Transportation West Inc.
- Construction start
- Feb 21, 2018(actual)
- Construction end
- May 31, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Oct 1, 2017
- Construction end4 weeks earlyforecast Jun 30, 2018