Back to projects

Transportation West Fleet Upgrade

Alberton, Prince Edward Island

completePublic TransitSCF
Federal contribution
$33,225
Federal share33%

of $99.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 25, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Transportation West Inc.
Construction start
Feb 21, 2018(actual)
Construction end
May 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Oct 1, 2017
  • Construction end4 weeks earlyforecast Jun 30, 2018

Also in Alberton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51807 in the federal list. How to read these figures.