Renewal of the service vehicle inventory
Federal contribution
$253,371
Federal share50%
of $506.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 16, 2018
20182019
Built
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- May 1, 2019(actual)
- Construction end
- Sep 30, 2019(actual)
Also in Québec