Back to projects

Renewal of the service equipment

Québec, Quebec

completePublic TransitPTIF
Federal contribution
$52,481
Federal share50%

of $105.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 16, 2018
201820192020
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 20, 2018(actual)
Construction end
Mar 31, 2020(actual)