Renewal of the service equipment
Federal contribution
$52,481
Federal share50%
of $105.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 16, 2018
201820192020
Built
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- Jun 20, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Québec