Back to projects

Terminus de la Faune (plans and specifications)

Québec, Quebec

completePublic TransitPTIF
Federal contribution
$106,259
Federal share50%

of $212.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 16, 2018
20182019
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Feb 1, 2018(actual)
Construction end
Mar 31, 2019(actual)

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51822 in the federal list. How to read these figures.