Redesign of the website
Federal contribution
$396,172
Federal share50%
of $792.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 16, 2018
201820192020
Built
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- May 1, 2017(actual)
- Construction end
- Jun 30, 2020(actual)
Also in Québec