Chrono - Equipment purchase phase and first wave of installation of a passenger information and operating assistance system in the buses of the Réseau de transport métropolitain (RTM)

Montréal, Quebec

completePublic TransitPTIF
Federal contribution
$6.8M
$6,807,490
Federal share50%

of $13.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 13, 2017
20182019202020212022
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 20, 2018(actual)
Construction end
Dec 31, 2021(actual)

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51832 in the federal list. How to read these figures.