Chrono Phase 6 - Integration of GIRO-Hastus and GIRO-ACCES components

Montréal, Quebec

completePublic TransitPTIF
Federal contribution
$4.2M
$4,183,619
Federal share50%

of $8.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2017
20182019202020212022
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Feb 14, 2018(actual)
Construction end
Jul 20, 2022(actual)