Addition of 2 Bike Stations
Federal contribution
$533,030
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 15, 2017
201820192020
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport métropolitain (RTM)
- Construction start
- Sep 18, 2018(actual)
- Construction end
- May 25, 2020(actual)
Also in Montréal