Back to projects

Water Treatment Plant Repairs in the Community of Dog Paw

Northwest Angle 33 First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$22,100
Federal share50%

of $44.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 30, 2019(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2.3 years lateforecast Jun 5, 2017

Also in Northwest Angle 33 First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51845 in the federal list. How to read these figures.