Stanley A. Milner Renewal & Upgrades Capital

Edmonton, Alberta

completeCultureNRP
Federal contribution
$2.0M
$2,000,000
Federal share18%

of $11.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 18, 2018
2017201820192020
Built

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Edmonton Public Library
Construction start
Jan 3, 2017(actual)
Construction end
Feb 12, 2020(actual)

Against the original forecast

  • Construction end5 months lateforecast Aug 30, 2019