Stanley A. Milner Renewal & Upgrades Capital
Federal contribution
$2.0M
$2,000,000
Federal share18%
of $11.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2018
2017201820192020
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Edmonton Public Library
- Construction start
- Jan 3, 2017(actual)
- Construction end
- Feb 12, 2020(actual)
Against the original forecast
- Construction end5 months lateforecast Aug 30, 2019