Purchase additional rolling stock
Federal contribution
$38,872
Federal share47%
of $82.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 11, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Municipality of Sioux Lookout
- Construction start
- Mar 14, 2017(actual)
- Construction end
- Apr 16, 2019(actual)
Against the original forecast
- Construction start8 months earlyforecast Nov 27, 2017
- Construction end5 months earlyforecast Sep 30, 2019
Also in Sioux Lookout