Drainage System Improvements
Nahanni Butte, Northwest Territories
Federal contribution
$125,000
Federal share50%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2018
today
201820202022202420262028
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Nahanni Butte First Nation
- Construction start
- Jun 1, 2024(actual)
- Construction end
- Sep 30, 2027(forecast)
Against the original forecast
- Construction start23 months lateforecast Jul 1, 2022
Also in Nahanni Butte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51883 in the federal list. How to read these figures.