Nahanni Butte Performance Stage
Nahanni Butte, Northwest Territories
Federal contribution
$237,000
Federal share75%
of $317.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 17, 2022
20232024
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Nahanni Butte Dene Band
- Construction start
- Jun 6, 2023(actual)
- Construction end
- Sep 30, 2024(actual)
Against the original forecast
- Construction start12 months earlyforecast Jun 1, 2024
- Construction end6 months earlyforecast Mar 31, 2025
Also in Nahanni Butte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63575 in the federal list. How to read these figures.