Acadia House
Federal contribution
$895,333
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 4, 2018
201820192020
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Comité permanent de développement du Juvénat Inc.
- Construction start
- Oct 30, 2019(actual)
- Construction end
- Nov 2, 2020(actual)
Against the original forecast
- Construction start8 months lateforecast Mar 4, 2019
- Construction end3 months earlyforecast Jan 30, 2021
Also in Petit-Rocher
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51899 in the federal list. How to read these figures.