Petit-Rocher - Water Treatment Plant
Federal contribution
$2.5M
$2,498,028
Federal share60%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 5, 2021
202120222023
Built
Approved 15 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Petit-Rocher
- Construction start
- Aug 4, 2020(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Jan 31, 2023