Schedule

Announced and approvedJun 1, 2018
20192020
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jun 21, 2018(actual)
Construction end
Sep 24, 2020(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2018
  • Construction end11 months lateforecast Oct 31, 2019