Schedule
Announced and approvedMar 15, 2018
20192020
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- Jun 13, 2018(actual)
- Construction end
- Aug 21, 2020(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2018