Bus Fleet Growth - Electric Buses

Edmonton, Alberta

completePublic TransitPTIF
Federal contribution
$21.6M
$21,563,000
Federal share50%

of $43.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 13, 2018
201920202021
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Edmonton
Construction start
Apr 1, 2018(actual)
Construction end
May 15, 2021(actual)

Against the original forecast

  • Construction start9 months lateforecast Jul 1, 2017