Fall River Water Servicing - Phase 2
Federal contribution
$1.4M
$1,441,583
Federal share32%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2018
20182019
Built
Approved 5 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Dec 18, 2018(actual)
Against the original forecast
- Construction start14 months earlyforecast Oct 18, 2018
- Construction end3 months earlyforecast Mar 31, 2019
Also in Halifax