Schedule
Announced and approvedMar 29, 2018
20182019202020212022
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Calgary
- Construction start
- Jan 31, 2018(actual)
- Construction end
- Mar 1, 2022(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Mar 31, 2022