Resurfacing of the Ottawa Valley Recreation Trail
Federal contribution
$39,370
Federal share50%
of $78.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 23, 2018
2018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- County of Lanark
- Construction start
- Oct 2, 2017(actual)
- Construction end
- Oct 20, 2017(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Oct 16, 2017
- Construction end8 weeks earlyforecast Dec 15, 2017