Rehabilitation of Existing Storm Sewers (Mississippi Mills)
Federal contribution
$33,000
Federal share46%
of $72.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Lanark
- Construction start
- Aug 27, 2017(actual)
- Construction end
- Dec 6, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end3 months lateforecast Sep 1, 2017
Also in Lanark
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48516 in the federal list. How to read these figures.