Business Plan Development Consulting Work
Federal contribution
$71,135
Federal share47%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 23, 2018
20192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Burlington
- Construction start
- Jan 14, 2019(actual)
- Construction end
- Jan 30, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast Oct 31, 2018
- Construction end8 weeks lateforecast Dec 2, 2019
Also in Burlington
- Halton Region Wastewater Treatment (Skyway Facility)$51.4M
- Replacement of Access Points; Open Concept Schools; Building Automation Systems & Controls Upgrade; Child Care Retrofits & Outdoor Spaces$6.9M
- Portable Classroom Ventilation Improvements; HVAC Improvements; Window Replacement$5.6M
- Improvements to HVAC, Windows, Bottle Filling Stations, Washrooms, Doors, Child Care Centre, WiFi and Network Infrastructure$5.4M
- Highway 403 - Rehabilitation and Resurfacing$4.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51974 in the federal list. How to read these figures.