Back to projects

Repaving of the parking lot at the operations centre (including the 2016 extension)

Lévis, Quebec

completePublic TransitPTIF
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2018
2019
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
May 27, 2019(actual)
Construction end
Oct 31, 2019(actual)