Construction of a Park-and-Ride Lot in the Buckingham Sector
Federal contribution
$695,654
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2018
20192020
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de l'Outaouais (STO)
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Gatineau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52032 in the federal list. How to read these figures.