LRT Renewal and Upgrades
Federal contribution
$16.2M
$16,181,774
Federal share50%
of $32.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 29, 2018
20172018201920202021
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Edmonton
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Dec 31, 2020(actual)
Also in Edmonton