Water Service Replacement
Federal contribution
$49,063
Federal share39%
of $125.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
2019
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Georgina
- Construction start
- Jul 1, 2019(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start14 months lateforecast May 15, 2018
- Construction end2 months earlyforecast Dec 31, 2019
Also in Georgina
- Georgina Water Treatment Plant Upgrade$2.4M
- Completing the Renovations to the Barn Area at Clearwater Farm$2.0M
- Watermain Replacement (Burke Street, Garrett Drive and West Street)$1.4M
- Georgina Island First Nation Water Plant Upgrade$1.4M
- Energy, Accessibility, and Climate Resiliency Retrofit of Sutton Arena$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52131 in the federal list. How to read these figures.