Back to projects

Philrobden Street Water main Replacement

Lambton Shores, Ontario

completeDrinking WaterCWWF
Federal contribution
$64,711
Federal share31%

of $210.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2018
201920202021
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 1, 2019(actual)
Construction end
Nov 27, 2020(actual)

Against the original forecast

  • Construction start17 months lateforecast Feb 15, 2018
  • Construction end10 months earlyforecast Sep 30, 2021

Also in Lambton Shores