Schedule

Announced and approvedAug 10, 2018
20192020202120222023
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jan 15, 2023(actual)
Construction end
Sep 20, 2023(actual)

Against the original forecast

  • Construction start20 months lateforecast May 15, 2021
  • Construction end3 weeks lateforecast Aug 31, 2023