Water System Improvements

Hickman's Harbour-Robinson Bight, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$55,916
Federal share33%

of $167.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
20192020
Built

Approved 16 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 19, 2019(actual)
Construction end
Jan 24, 2020(actual)

Against the original forecast

  • Construction end22 months earlyforecast Nov 30, 2021