Water System Improvements – Phase 2 - Hickman's Harbour

Hickman's Harbour-Robinson Bight, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$63,253
Federal share40%

of $158.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 20, 2021(actual)
Construction end
May 31, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 15, 2021
  • Construction end2 weeks lateforecast May 15, 2022