Water System Improvements Phase 2 - Hickman's Harbour
Hickman's Harbour-Robinson Bight, Newfoundland and Labrador
Federal contribution
$63,253
Federal share40%
of $158.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Local Service District of Hickman's Harbour-Robinson Bight
- Construction start
- Jul 20, 2021(actual)
- Construction end
- May 31, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 15, 2021
- Construction end2 weeks lateforecast May 15, 2022
Also in Hickman's Harbour-Robinson Bight
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56782 in the federal list. How to read these figures.