Taylor's Lane/Anderson's Lane Storm Sewer Replacement and Reconstruction

Channel-Port aux Basques, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$96,567
Federal share23%

of $417.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jul 15, 2019(actual)
Construction end
Oct 30, 2020(actual)

Against the original forecast

  • Construction start10 months earlyforecast May 15, 2020
  • Construction end2 weeks earlyforecast Nov 15, 2020